Project type
Water
Project phase
Construction
Project contact
communications@lakecountry.bc.ca
Active construction project
No
Schedule
March 2025 – End of June 2025
Location
Beaver Lake Road, just east of Jim Bailey Road
Project budget
$1,300,000
Project status
Complete
Project description
The City of Kelowna Bulk Metering Facility project separated the City of Kelowna and District of Lake Country infrastructure at the District’s boundary and established a dedicated metering point between the two systems, as the District currently supplies water to the Kelowna Industrial Park. Additionally, underground infrastructure was brought above-ground to improve worker safety by eliminating confined space entry risks.